Monthly site progress reports, third-party quality audit results, and photographic records for 64 BharatKunj, Erandwane.

Oct 2025Latest Update
Floor 8Current Progress
100%Foundation & Podium
M30Concrete Grade
Monthly Reports

Site Progress Timeline

Project Overview →
Floor 8 Slab Cast Complete
Oct 2025

Floor 8 Slab Cast Complete

Floor 8 slab successfully cast and cured. Concrete grade M30 confirmed by third-party cube test (compressive strength 36.2 MPa at 28 days). Internal brick work on floors 1–4 progressing. External plastering on lower floors completed.

Floor 7 Complete — MEP Begins
Sep 2025

Floor 7 Complete — MEP Begins

Floor 7 structural work complete. MEP (mechanical, electrical, plumbing) rough-in work commenced on floors 1–3. Conduit laying and drain pipe installation in progress. Waterproofing in bathrooms underway on lower floors.

Third-Party Quality Audit Completed
Aug 2025

Third-Party Quality Audit Completed

Independent structural audit conducted by M/s. Structural Associates. All parameters — concrete cover, rebar placement, slab thickness — confirmed compliant with IS 456:2000. Full report available to registered buyers.

Floors 5 & 6 Structural Work
Jul 2025

Floors 5 & 6 Structural Work

Floors 5 and 6 columns, beams, and slabs completed. 400+ cubic metres of M30 concrete poured across both floors. Steel reinforcement sourced from SAIL (ISI-marked Fe500D) — test certificates on file and available on request.

Window & Door Frames Installation
Jun 2025

Window & Door Frames Installation

UPVC window frames installed on floors 1–3. Solid wood main door frames fixed and treated against moisture. External window openings measured and verified against approved drawings on all lower floors.

Brickwork Floors 1–3 Complete
May 2025

Brickwork Floors 1–3 Complete

100% brickwork (230mm AAC block with cement mortar) completed on floors 1, 2, and 3. Internal plastering commenced on ground floor. All wall reinforcements confirmed before plastering.

Floors 3 & 4 Structural Complete
Apr 2025

Floors 3 & 4 Structural Complete

Structural work on floors 3 and 4 completed on schedule. Electrical conduit routing approved by PMC. Site team maintained 6-day work week to remain ahead of schedule. 100% safety nets installed on all open floors.

Foundation Complete — Raft Pour
Mar 2025

Foundation Complete — Raft Pour

Raft foundation fully cast. 620 cubic metres of M35 concrete poured over 18 hours in a single continuous pour. Concrete pump, batching plant, and 40 labourers coordinated. Settlement monitoring initiated — all readings nominal.

Excavation & Pile Work
Jan 2025

Excavation & Pile Work

Site excavation completed. 48 bored cast-in-situ piles (600mm dia, 18m depth) executed and pile load tests completed. All piles passed 2x design load test. Raft reinforcement binding in progress.

Bhumi Puja — Groundbreaking
Jun 2024

Bhumi Puja — Groundbreaking

Official groundbreaking ceremony held on 12 June 2024. Mr. Ajit G. Nahar performed the Bhumi Puja with registered buyers and team members present. MahaRERA registration confirmed. Construction commencement intimation submitted to PMC.

Quality Assurance

Third-Party Verified at Every Stage

Every material and structural element at 64 BharatKunj is independently tested and verified. We publish results openly — no editing, no cherry-picking.

Concrete Cube Tests
28-day compressive strength. All cubes exceed M30 target — test certificates available.
Rebar Tensile Tests
Fe500D yield strength verified. SAIL mill test certificates on file.
Pile Load Tests
100% of 48 piles tested at 2x design load. Zero failures.
Structural Audit
Full IS 456:2000 compliance audit by independent structural engineer. Report available to buyers.
Waterproofing Tests
Flood test (24-hour ponding) on all terraces and bathrooms before handing over.
MahaRERA Escrow

Your Money is Protected

Under MahaRERA, 70% of all buyer collections are deposited in a dedicated escrow account. Withdrawals are only permitted against certified construction completion certificates issued by PMC.

MahaRERA Commitment
70% escrow — verified on maharera.mahaonline.gov.in
Possession date penalty: Rs.500/sq ft/month for delay
All approvals, plans, and agreements registered on RERA portal
Independent engineer quarterly construction certificate
Buyer grievance addressed within 30 days by law

Registered buyers get WhatsApp updates and full photo access each month.